4. Periodic Maintenance
4.1 Periodic Cable Check
Periodically perform a cable check:
1. Ensure that the cables have not loosened. Use a wrench or socket to tighten any connections or
terminals that have come loose.
2. Ensure that no wires have pinched or frayed; especially the balance wires.
4.2. Periodic Voltage Check
If the battery pack has gone unused for more than 6-12 months, it is recommended to check the cell voltages
with a multimeter. If they are low, charge the battery pack until the voltages are around 50-80%.
Use the iPhone / Android app and the bluetooth module to ensure that the cell voltages are not different by
more than XXXX millivolts when fully charged. If the cells are off by more than a few millivolts, first verify with
an external voltmeter. If the voltmeter doesn’t agree, then the BMS may need calibration (follow the steps in
Section 4). Otherwise, a top-balance might be necessary to bring them closer together. See Section 2.3 for
the top-balancing procedure.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Overkill Solar BMS Series and is the answer not in the manual?

Overkill Solar BMS Series Specifications

General IconGeneral
BrandOverkill Solar
ModelBMS Series
CategoryControl Unit
LanguageEnglish

Related product manuals