6-3
6.2 Preparing for operation
6 Commissioning
6.2.3 Commissioning the PNOZmulti safety system
Commissioning the PNOZmulti safety system6-Verdrahtung_multi_Basis_Betr_erstes_Mal_mini_multi_BA
Procedure:
Wire the inputs and outputs on the base unit in accordance with the
circuit diagram.
Connect the supply voltage:
Supply voltage for the units:
Terminal A1: + 24 VDC
–Terminal A2: 0 V
Supply voltage for the semiconductor outputs:
24 V terminal: + 24 VDC
0V terminal: 0 V
Note: The supply voltage for the semiconductor outputs must always be
present, even if you are not using the semiconductor outputs.
6.2.3.1 Load project from chip card
Load project from chip card6-Verdrahtung_mini_multi_Basis_Betr_erstes_Mal_von_Chipkarte_BA
Procedure:
Insert the chip card containing the current project into the card slot on
the base unit.
Switch on the supply voltage. The LC display shows the project
name, CRC sum and the date the project was created. Please check
this information.
Load the project by pressing the rotary knob. For the project to be
downloaded, the rotary knob must be held down for between 3 and 8
seconds. Once the project has been successfully downloaded, the
status of the inputs and outputs will be shown on the display.
6.2.3.2 Load project via USB port
Load project via USB port 6-Verdrahtung_mini_multi_Basis_Betr_erstes_Mal_USB_BA
Procedure:
Insert a chip card into the card slot on the base unit.
Connect the computer containing the PNOZmulti Configurator to the
base unit via the USB port.
Switch on the supply voltage.
Download the project (see PNOZmulti Configurator's online help).
Once the project has been successfully downloaded, the status of the
inputs and outputs and the supply voltage will be shown on the dis-
play. The "RUN" LED will be lit.