6-- 1
Powerware 9315 (500 kVA--750 kVA) T1 and T3 Installation Addendum
164201244--001 REV. A 011500
Dielectric Testing
6.1 Dielectric Test Procedure After Transformer
Replacement
This document specifies the procedure steps to be taken to perform a Dielectric
Voltage Withstand test for the 750 product line after the power transformers T1 and
T3 have been removed and replaced.
CAUTION:
Risk of Electric Shock – The procedure you are about to follow places a
high voltage from conductive to grounded parts of the Unit Under Test
(UUT). This voltage could shock either yourself or bystanders. You
should never touch the UUT when the test is underway and notify
bystanders about the test you will be conducting.
6.2 Equipment
Refer to Chapter 1 Getting Started for equipment requirements.
6.3 UUT Preparation
If a single module (RT) system is being tested, proceed to paragraph 6.3.1; if a
multi-module system is being tested, proceed to paragraph 6.3.2.
6.3.1 Single Module (RT) Preparation
To prepare a single module UPS system for testing, perform the procedures in the
following paragraphs.
6.3.1.1 Installing UPS Internal Power and Control Wiring
NOTE: The cables used in steps 3 through 5 are coiled inside the Input/Rectifier
cabine t and are attached at the factory to the output of the rectifier. The
cables used in steps 8 and 9 are c oiled inside the Module Bypass Cabinet
(MBC) and are attached at the factory to the input of the MBC.
6