EB 3018 EN 3-5
Design and principle of operation
3.1 Additional ttings
Î See Fig.3-4
Pressure gauges
Install a pressure gauge (3 and 5) at suitable
points to monitor the pressures prevailing in
the plant.
Bypass and shut-off valves
We recommend installing a shut-off valve (1
and 6) both upstream of the strainer and
downstream of the regulator and installing a
bypass line. The bypass ensures that the
plant does not need to be shut down for ser-
vice and repair work on the regulator.
Indirect connection to district heating system with Type42-36E PICV:
12
6498
1 Shut-off valve
2 Strainer
3 Pressure gauge (ow pipe)
4 Type42-36E PICV
5
Pressure gauge (return ow
pipe)
6 Shut-off valve
8 Needle valve
9 Electric actuator
Fig.3-4: Type42-36E (installation example)