14-1
OP27,
OP37 Equipment Manual
Release 05/99
Commissioning
The
commissioning guide below explains the individual steps for commission
-
ing the OP27 and OP37. Figure 14-1 provides a diagram of the most important
steps for initial startup, recommissioning and normal operation of the OP
.
T
ransfer configuration data to the OP
COM1/2
Set the OP to Download mode in the
startup phase (refer to Section 14.2)
Switch on the OP power supply
Initial startup
Neither a configuration nor
firmware is available on the
OP.
Recommissioning
The OP already has a config
-
uration but must now use a
new configuration or firmware.
Normal operation
The OP is operated with the
loaded configuration.
Start screen
ProTool
IF2
OP
Figure 14-1 Commissioning flowchart
Flowchart
14