4.6 Wiring Sequence
Power Module PM230 IP55
46 Hardware Installation Manual, 2010-07-02, A5E02923635A AB
Before the wiring of the Power Module can be performed, the following actions should be
taken:
1. The Power Module must be mounted correctly as previously describe in this manual.
2. The Power Module cover has been removed.
3. The Control Unit has been fitted correctly to the Power Module.
4. The Installer has reviewed the following instructions to ensure that all the necessary
tools, to complete the wiring sequence, are available.
5. The Installer must be fully conversant with all necessary local and national safety
regulations regarding electrical installation of industrial products.
Wiring sequence
To perform the correct wiring sequence, the following actions must be taken:
Step 1
Prepare the cables according to the dimensions
given in the previous section of this manual.
*ODQGSODWH
$
%
&
'
Step 2
1. Remove the retaining screws from the gland
plate.
2. Remove the gland plate.
Step 3
1. Fit the cable glands to the cables.
2. Ensure that the cable glands are unscrewed
and the cables can move freely through the
cable glands.
An EMC cable gland is required to be fitted to the
motor power cable and the Control Unit cable to
ensure EMC compliance.