Connecting
4.5 Cable preparation
Power Module PM230 IP55
Hardware Installation Manual, 2010-07-02, A5E02923635A AB
45
4.5 Cable preparation
Preparation information
The table and the diagram below are provided to ensure that the cables for use with the PM
power and motor terminals are prepared correctly.
No screening dimensions are given for the input power cables as these are not normally
screened cables.
Dimensions Diagram Cable type
A B C D
FSA power cable 10 mm
0.39 inches
60 mm
2.36 inches
- 90 mm
3.54 inches
FSA motor cable 10 mm
0.39 inches
60 mm
2.36 inches
10 mm
0.39 inches
60 mm
2.36 inches
FSB power cable 10 mm
0.39 inches
60 mm
2.36 inches
- 50 mm
1.96 inches
FSB motor cable 10 mm
0.39 inches
50 mm
1.96 inches
10 mm
0.39 inches
40 mm
1.57 inches
FSC power cable 10 mm
0.39 inches
50 mm
1.96 inches
- 70 mm
2.75 inches
*ODQGSODW
$
%
&
'
FSC motor cable 10 mm
0.39 inches
50 mm
1.96 inches
10 mm
0.39 inches
40 mm
1.57 inches
4.6 Wiring Sequence
Overview
Due to the nature of the Power Module enclosure, the following guidelines are given to
provide a more effective and efficient sequence to ensure that the wiring of the Power
Module is completed correctly.
Prerequisite actions
DANGER
Ensure the Power Module has no power connect prior to installing cables and wiring
It is essential that during the installation phase of the cables and wiring of the Power
Module that no power, in any form, is connected to the Power Module or the attached
Control Unit.
If power has been applied to the Power Module or the Control Unit this MUST be
disconnected. Once the power has been removed, the user should wait for at least 5
minutes before proceeding with the electrical installation of the Power Module.