6 Preparation for Installation SMA Solar Technology AG
20 SCCPXT-IA-D7-en-42 Installation Manual
6 Preparation for Installation
6.1 Selecting a Mounting Location
6.1.1 Requirements for the Mounting Location
If the Sunny Central is to be installed in an electrical equipment room, an adequate supply of fresh air must be
ensured. If this is not the case, an additional ventilation system must be installed, e.g. an external fan.
The mounting location must be freely accessible at all times.
The mounting location must be below the maximum installation altitude (see Section17 "Technical Data", page76).
The ambient temperature must be within the operating temperature range (see Section17 "Technical Data",
page76).
The mounting location must fulfill the requirements for the ambient conditions (see Technical Information "Installation
Requirements - Important information on transportation and installation for Sunny Central 500CP XT ⁄ 630CP XT ⁄
720CP XT ⁄ 760CP XT ⁄ 800CP XT ⁄ 850CP XT ⁄ 900CP XT").
6.1.2 Dimensions of a Sunny Central
Dimensions of a Sunny Central for Outdoor Installation
Figure5: Dimensions with roof

Table of Contents