7 Transporting the Sunny Central SMA Solar Technology AG
32 SCCPXT-IA-D7-en-42 Installation Manual
7. Release the grounding cables from the Sunny Central.
8. Remove the Sunny Central roof and set down on a suitable surface.
7.7.2 Transporting the Sunny Central Using a Crane
Requirements:
☐ The crane and hoist must be designed to take the weight of the Sunny Central.
☐ The hoist must be properly connected to the crane.
☐ The roof of the Sunny Central must be dismantled.
Procedure:
1. Attach the hoist to all four lifting eyes in the Sunny Central.
2. Raise the crane hook slowly until the hoist is taut.
3. Ensure that the hoist is attached correctly.
4. Slightly raise the Sunny Central.
5. Transport the Sunny Central as close to the ground as possible.
6. Transport the Sunny Central to the mounting location and set down on a suitable surface.
7.7.3 Mounting the Roof of the Sunny Central
Danger of crushing due to heavy, unwieldy roof
The roof of the Sunny Central is unwieldy and weighs 30 kg. If you try to move the roof on your own, you run a risk of
having limbs crushed.
• Only move the roof with at least two persons.