SMA Solar Technology AG 7 Transporting the Sunny Central
Installation Manual SCCPXT-IA-D7-en-42 33
Procedure:
1. Position the roof on the Sunny Central.
2. Screw the grounding cable onto the Sunny Central
(torque: 14.2 Nm).
3. Slide the roof into the rail on the Sunny Central and pull forwards.
4. Press the roof downwards.
5. Insert the left-hand ventilation grid.
6. Screw the left-hand ventilation grid on (torque: 20 Nm).
7. Insert the right-hand ventilation grid.