SMA Solar Technology AG 16 Decommissioning
Installation Manual SCCPXT-IA-D7-en-42 75
16 Decommissioning
1. Disconnect the Sunny Central from all voltage sources (see Section14, page65).
2. Disassemble the panels (see Section8.3, page35).
3. Screw the protective cover over the fuses.
4. Decommission the DC main distribution (see DC main distribution documentation).
5. Decommission the DC sub-distributions (see DC sub-distribution documentation).
6. Disconnect the AC and DC cabling in the Sunny Central.
7. Mount the panels (see Section 15.8).
8. Close the door of the interface cabinet.