SMA Solar Technology AG (First) Commissioning
Technical Description SI2012_2224-TEN082311 79
Overview of System Configurations:
2)
The system configuration is described extensively in chapter 7.7 "Configuring a System with Several
Sunny Islands" (Page 68).
2)
These applications are only possible with firmware versions 3.0 and above.
Displayed Text Meaning
1phase 1SI single-phase system, 1 Sunny Island
1phase 2SI single-phase system, 2 Sunny Islands
1phase 3SI single-phase system, 3 Sunny Islands
Three 3SI 3-phase system, 3 Sunny Islands
8. After entering the parameters, the following
message appears on the display:
"Init Device OK
START?"
9. Confirm the question:
Press and hold the pushbutton on the Sunny
Remote Control 1.
10. The following message appears:
„ST(A)NDBY: To Start INV(erter) hold <Enter>“
The QCG is complete.
To start the Sunny Island:
11. Press and hold the pushbutton on the Sunny
Remote Control 1.
During this procedure a bar appears on the
display.
12. When the bar on the display disappears and the
Sunny Remote control emits a tone signal:
Let go of the Sunny Remote Control pushbutton.
13. The Sunny Island starts.
The Sunny Island is in operation.
Init Device OK
START?
STNDBY: To Start
INV hold <Enter>