6. COMMISSIONING
6.1. Startup / Shutdown Procedure
The inverter must be installed by a qualified / licensed electrical engineer in accordance
to the countries wiring regulations.
Before switching on, the installation engineer must have completed the Earth Bond, RCD and
earth leakage tests, checked that the solar panel Voc voltage does not exceed 480V and checked
the battery voltage.
Power on Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator)
Shutdown Sequence:
1) Switch off AC
2) Press the start button
3) Switch off the battery and the battery breaker
4) Switch off the DC (PV isolator)
6.2. Information for Commissioning the Inverter
After you have successfully powered up the inverter, it must be programmed and set up
as per the programming feature above.
COMMISSIONING

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SunSynk SUNSYNK-6K-SG02LP1 and is the answer not in the manual?

SunSynk SUNSYNK-6K-SG02LP1 Specifications

General IconGeneral
BrandSunSynk
ModelSUNSYNK-6K-SG02LP1
CategoryInverter
LanguageEnglish

Related product manuals