TSC 80e TRANSFER SWITCH CONTROLLER
PM091 Rev 0 09/01/21 Thomson Technology
14
3. OPERATING INSTRUCTIONS
To operate the TSC 80e controller and associated transfer switch using the front faceplate
pushbuttons, refer to the following detailed operating instruction sub-section descriptions.
3.1. AUTOMATIC SEQUENCE OF OPERATION
3.1.1. NORMAL OPERATION
Under normal operating conditions, the transfer switch operates automatically during a
failure and restoration of utility power and does not require operator intervention.
When utility supply voltage drops below a preset nominal value (70 - 95% of rated
adjustable) on any one phase, an engine start delay will be initiated and the transfer to
utility supply signal will be removed (i.e. contact opening). Following expiry of the
engine start delay period (0 - 60 sec. adjustable) an engine start signal will be given
(contact closure, relay drops out to initiate start sequence).
Once the engine starts, the transfer switch controller will monitor the generators
voltage and frequency levels. When the generator voltage and frequency rises above
preset values (70 - 95% nominal adjustable) the Engine Warm-up timer will be
initiated. After the Engine Warm-up timer expires (0-60 sec. Adjustable), the transfer to
generator supply signal (contact closure) will be given to the transfer switch
mechanism. The load will then transfer from the utility supply to the generator supply
via motor driven mechanism (Neutral Delay is bypassed on utility failure detection).
The generator will continue to supply the load until the utility supply has returned and
the retransfer sequence is completed as follows: When the utility supply voltage is
restored to above the present values (70 - 95% of rated adjustable) on all phases, a
transfer return delay circuit will be initiated. Following expiry of the utility transfer
return timer (0 - 30 min. adjustable), the transfer to generator supply signal will be
removed (contact opening), then the transfer to utility supply signal (contact closure)
will be given to the transfer switch mechanism. The load will then be transferred from
the generator supply back to the utility supply. During the utility re-transfer sequence a
neutral positioning delay circuit will cause the transfer mechanism to pause in the
“neutral position (i.e. with both transfer power switching devices open) for the duration
of the neutral delay timer (0-30 seconds adjustable) setting. Once the neutral delay
expires, the re-transfer sequence will be completed.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the THOMSON TSC 80E - V2.1 and is the answer not in the manual?

THOMSON TSC 80E - V2.1 Specifications

General IconGeneral
BrandTHOMSON
ModelTSC 80E - V2.1
CategoryController
LanguageEnglish

Related product manuals