Introduction
Bench Test
1-3
P/N: 1049060-01
Required Tools
MC Systems Calibration Kit, P/N 1031278-01
Metric wrench set
English wrench set
Allen wrench set (English and metric)
Drill
Hole saw
Grinder
Sharp utility knife
Wire cutters
Standard screwdriver
Tape measure
Permanent marker or another marking pen
Smart Level
Spray paint (if needed, color to match machine paint)
Required Personnel
A qualified welder is required to install brackets for mounting system components and hose clamps
for system cables. Be sure to arrange for a qualified welder to be on site for the planned installation.
Bench Test
A Bench Test procedure should be performed in advance of the actual machine installation.
Machine Inspection
Perform a machine inspection to confirm that the dozer is in an acceptable condition for machine
control applications.
Look for any damage that would prevent the installation and operation of the components.
Ask the operator to perform machine movements to confirm that the hydraulic system operates
within normal parameters.
Component Installation Locations
Identify all sensors and bracket installation locations.
For complete information about performing a Bench Test, refer to the Bench Test
procedure described in the MC-X Dozer Systems Reference Installation and
Calibration Manual (P/N 1044736-01).
It is important to consider freedom of movement for various machine parts
when routing cables, as well as the potential for debris striking installed
components.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Topcon MC-X3 and is the answer not in the manual?

Topcon MC-X3 Specifications

General IconGeneral
BrandTopcon
ModelMC-X3
CategoryControl Systems
LanguageEnglish

Related product manuals