DRIVE INSTALLATION DRAWINGS (cont’d)
Frame 2 drive lifting and assembly
XFMR TOP LIFT
USE XFMR LIFTING EYES THRU ROOF
TOW MOTOR SLOTS
CUBICLES BOTTOM LIFT
CONNECT
(3) 3 PHASE
(1) GROUND
(9) DC BUSSES
WITH BUS SPLICES
1/2" BOLT TOGETHER HOLES (6)
AND MOUNTION HOLES
FAN CONTROL/POWER WIRE CONNECTOR
USE LIFTING ANGLE - ONLY WITHOUT CELLS INSTALLED
INV TOP LIFT
WIRE ACCESS
LOWER CONTROL
THEN INSTALL AND WIRE THE FAN ASSEMBLIES.
AFTER THE SECTIONS ARE IN PLACE BOLT TOGETHER WITH
NOTE : OVERHEAD LIFTING PROVISIONS ARE ALSO PROVIDED
MAKE SURE THE FORKS EXTEND ENTIRELY THROUGH THE SECTION.
LIFT FROM THE SLOTS IN THE CHANNEL BASE ON EACH SECTION.
TO MOVE THE SECTIONS USE A FORKLIFT OF ADEQUATE CAPACITY
WITH 1/2" HARDWARE.
FAN ASSEMBLY