DRIVE INSTALLATION DRAWINGS (cont’d)
Frame G4P module lifting and installation continued
Power Module Installation
1. Lower lifter tray to ground. Roll Power Module onto tray. Secure with chains.(F)
2. Raise tray above Power Module support pan. Lower tray, inserting pins into
holes in front edge of support pan. (E) Set truck brake.
3. Unlatch chains. Roll Power Module by handles from truck onto enclosure rail
until enclosure and Power Module bus stabs touch.
4. Install (1) bolt 'D' at back of cableway. Unlock, remove truck.
5. Install (5) bolts 'C' through bus stabs ACN, P, C, N & ACL. Torque all power
connections (5/16-18 hdwr) to 10-15 ft-lbs.
6. Connect Control Power Cable from wireway as shown at 'B'.
7. Connect Control Cable from wireway to PCB as shown at 'A'.
8. Close upper Power Module cover. Secure with 2 bolts.
9. Replace outside filter cover.
E
F
Pin in front
edge of lift
tray
Power
Module
support pan
For lifting the Power Module after it is out of
the Cubicle use Lifting Attachment
GCI6723G054 and a lifting device rated at
1000 lbs. or more.
Secure Lifting Attachment to Power Module
with (4) ½-13 Bolts.
Lifting
Attachment