24 BAS-SVX44A-EN
Configuration Option Setup
Installation Options
Table 7. Installer configuration setup menu
Opt.
No.
Name Def Values/Descriptions Notes
0100
Tem pe ra tu re in di ca ti on/
Resolution
0 • 0= °F, 1 degree resolution
• 1= °F, 0.5 degree resolution
• 2= °C, 1 degree resolution
• 3= °C with 0.5 degree resolution
• 4= °C with 0.1 degree resolution
This setting affects indoor temperature display and setpoint display
resolutions. Outdoor temperature display area is always ±1 resolution
for both F and C. Refer to Option 0210.
0110
Clock Format 12 • 12= 12-hour clock • 24= 24-hour clock
0120
Year 11 • 11–99
Available year range: 2011–2099. This value is updated to the real time
clock after setting. Day of the week is updated automatically.
0121
Month 1 • 1–12
This value is updated to the real time clock after setting. Day of the week
is updated automatically.
0122
Day 1 • 1–31
Month dependent: this value is updated to the real time clock after
setting. Day of the week is updated automatically.
0125
Daylight Savings 2 • 0= Disabled
• 1= US (1987), changeover at
2:00am
• 2= US (2007), changeover at
2:00am
• 3= Europe, changeover at 1:00am
• 4= Manual, changeover at 2:00am
0126
0127
0128
0129
• Spring Ahead Month
• Spring Ahead Day
•Fall Back Month
•Fall Back Day
•03
•01
•11
•01
• 01-12
• 01-31
• 01-12
• 01-31
Options available only if 0125 is set to 4.
0130
System Selection 8 • 1= 1H/1C (Conv) 1st Stage Heat
(W), 1st Stage Comp (Y), Fan (G)
• 2= 1H/1C (HP) 1st Stage Comp (Y),
Changeover (O/B), Fan (G)
• 3= 1H (Conv) 1st Stage Heat (W),
without fan
• 4= 1H (Conv) 1st Stage Heat (W),
Fan (G)
• 5= 1C (Conv) 1st Stage Comp (Y),
Fan (G)
• 6= 2H/1C (HP) 1st Stage Comp (Y),
Changeover (O/B), Auxiliary Heat
(W1), Fan (G)
• 7= 2H/2C (Conv) 1st & 2nd Stage
Heat (W,W2), 1st & 2nd Stage Comp
(Y,Y2), Fan (G)
• 8= 2H/1C (Conv) 1st & 2nd Stage
Heat (W,W2), 1st Stage Comp (Y),
Fan (G)
• 9= 1H/2C (Conv) 1st Stage Heat
(W), 1st & 2nd Stage Comp (Y,Y2),
Fan (G)
• 10= 2H/2C (HP) 1st & 2nd Stage
Comp (Y,Y2), Changeover (O/B), Fan
(G)
• 11= 3H/2C (HP) 1st & 2nd Stage
Comp (Y,Y2), Changeover (O/B),
Auxiliary Heat (W1), Fan (G)
0140
Schedule Options 1 0=Non-programmable 1= Programmable
0150
TOD/Economizer Output
(Terminal A)
0 • 0= Unused
•1= TOD energizes terminal A during
occupied period, not during
unoccupied period.
• 2= Economizer energizes terminal A
during a call for cool.
TOD is not available in Non-programmable Mode. (Refer to Option 0140)
0151
Heat Fan Operation 0 0= System controls fan 1= Thermostat controls fan
Only shown for conventional system with heat stages and fan capability.
For heat pump, the fan relay operates with thermostat control.
0153
Reversing Value O/B 0 0= O/B ON when call for cool 1= O/B ON when call for heat
Only shown for heat pump systems.
0160
Cycles Per Hour (CPH)
[First Stage Compressor]
3 1–5
Only for systems with cool or HP stage. (Refer to Option 0130.) Selection
in this stage changes 2nd stage cool default CPH.
0161
CPH (Second Stage
Compressor)
3 1–5
Only for systems with 2-cool or HP stages. (Refer to Option 0130.)