48
CONSERVAFLASH
Ensure the pre-formed soaker is clipped
into the starter bar. At this stage it is easiest
to mark and cut out for the lead ashing.
For best results always grind a 35mm deep
slottoallowConservaashtobeletintothe
wall. Brush out any dust from the channel.
Trialtthesteppedashing.Startinstalling
from the gutter towards the ridge. Apply
sealant (clear or grey low modulus neutral
cure) along the two internal weather bar
grooves.
The unique integral mechanical retention
wedge clips bite into the brickwork ensuring
positive location. Insert the next stepped
ashing (using sealant on the back),
ensuring it overlaps to marked minimum.
Continue up the roof, both slopes, with
steppedashings.
Oer up the horizontal ashing which
should typically sit two courses above the
steppedashing.Trimtosuittheroofpitch.
Use appropriate sealant, MS polymer if self
cleaning glass. Always seal the surface of
lead ashing to prevent run o onto self
cleaning glass.
Place Conservaash into the ground out
mortar joint at the gutter end, ensuring
loweredgelocatesintothe‘J’soaker.
Havingaddedlast steppedashingseach
side of the ridge ‘Butter’ the reverse side
of the saddle trim and place over the ridge
body.
1 2 3
4 5
6
Pre-formed soaker Stepped flashings (L & R)
Saddle apron Horizontal flashing
To be used on duo-pitch roofs
To be used on lean-to & Ultralite & above
the saddle apron on duo-pitch roofs
To be used on duo-pitch roofsTo be used on duo-pitch roofs