Run 9
________________________________________________________________________________________
_______________________________________
9-41
This method enables either for two panels to be loaded in pendulum with the aggregate
automatically moving to the second panel on completion of the first (cycling back and forth
thereafter.
Alternatively for large panels, a park position can be set for position 2 that will move the
head away from the panel on completion to allow unloading and loading a new panel.
When the new panel is loaded, pressing the switch field key (943) followed by the Move to
Position key (942) will move the aggregate back into the start position.
Always ensure that the aggregate is positioned clear of the workpiece and any other
table obstructions such as vacuum cups before commencing a cycle to prevent
damage to the aggregate.
CAUTION !
944
945
946
941
919
918
956
942
943