Installation and operating instruction
Gas burner WG10…/0-D ZM-LN
7 Commissioning
83300902 1/2019-02 La
44-112
Fourth test phase
In the fourth test phase, the joint to the mixing head 1 is tested for soundness. The
test phase can only be carried out during or after burner commissioning.
A leak detecting spray or electronic gas detector should be used for testing.
Use only leak detecting foam solutions, which do not cause corrosion, see DVGW-
TRGI, worksheet G600.
Check all components, intersections and test points of the gas valve train
between multifunction assembly and burner.
Document result of the soundness test on the engineers report.
Test points
1 Pressure into valve 1
2 Pressure between valve 1 and valve 2
3 Pressure after valve 2