Installation
54
Lead the control cables through the lead-through plate:
1. Cut holes in the grommets to fit them tightly onto the control cables.
2. Lead the control cables through the lead-through plate and slide the grommets onto the cables.
Terminal ABAB
hole 1 hole 2 hole 3 hole 1 hole 2 hole 3
mm mm mm mm in. in. in. in.
Frame size R8
U1 432 387 342 40 17.0 15.2 13.5 1.6
V1 148 5.8
W1 264 10.4
U2 284 239 194 40 11.2 9.4 7.6 1.6
V2 148 5.8
W2 264 10.4
UDC- 136 91 46 40 5.4 3.6 1.8 1.6
R- 148 5.8
UDC+/R+ 264 10.4
PE terminal hole 1 2 3 4 5 6 7 8 9
C / mm [in.] 24 [0.9] 56 [2.2] 88 [3.5] 120 [4.7] 152 [6.0] 184 [7.2] 216 [8.5] 248 [9.8] 280 [11.0]
Frame size R8
64605569
PE