EasyManua.ls Logo

ABB RELION RET670 - Interlocking for Busbar Grounding Switch BB_ES (3)

ABB RELION RET670
1016 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
en04000503_ansi.vsd
Section 1 Section 2
A1A2_DC(BS)
B1B2_DC(BS)
BH_LINE
(WA1)A1
(WA2)B1 B2
A2
BH_LINE
BH_LINE BH_LINE
ANSI04000503 V1 EN-US
Figure 350: Busbars divided by bus-section disconnectors (circuit breakers)
The project-specific logic is the same as for the logic for the double-breaker
configuration.
Signal
S1DC_OP All disconnectors on bus-section 1 are open.
S2DC_OP All disconnectors on bus-section 2 are open.
VPS1_DC The switch status of disconnectors on bus-section 1 is valid.
VPS2_DC The switch status of disconnectors on bus-section 2 is valid.
EXDU_BB No transmission error from breaker and a half (BH) that contains the above
information.
15.3.7 Interlocking for busbar grounding switch BB_ES (3)
IP14164-1 v4
15.3.7.1 Application
M15015-3 v7
The interlocking for busbar grounding switch (BB_ES, 3) function is used for one
busbar grounding switch on any busbar parts according to figure 351.
89G
en04000504.vsd
ANSI04000504 V1 EN-US
Figure 351: Switchyard layout BB_ES (3)
M15053-4 v4
The signals from other bays connected to the module BB_ES are described below.
Section 15 1MRK 504 163-UUS A
Control
744 Transformer protection RET670 2.2 ANSI
Application manual

Table of Contents

Related product manuals