EasyManuals Logo

ABB REQ650 Commissioning Manual

ABB REQ650
150 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #101 background imageLoading...
Page #101 background image
V-Bus1
V-Line1
N
Test
equipment
IED
V-Bus1
N
ANSI11000273-2-en.vsd
N
VMeasure
Ph/N
Ph/Ph
V-Bus2
V-Line2
V-Bus2
V-Line2
V-Line1
ANSI11000273 V2 EN
Figure 14: General test connection for a breaker-and-a-half diameter with one-
phase voltage connected to the line side
6.7.1.1 Testing the synchronizing function
This section is applicable only if the synchronizing function is included.
The voltage inputs used are:
V-Line
VA, VB or VC line 1 voltage inputs on the IED
V-Bus Bus voltage input on the IED
Testing the frequency difference
The frequency difference is in the example set at 0.20 Hz on the local HMI, and the test
should verify that operation is achieved when the FreqDiffMax frequency difference is
lower than 0.20 Hz. The test procedure below will depend on the settings used. Input
STARTSYN must be activated during the test.
1. Apply voltages
1MRK 505 293-UUS A Section 6
Testing functionality
93
Commissioning manual

Table of Contents

Other manuals for ABB REQ650

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB REQ650 and is the answer not in the manual?

ABB REQ650 Specifications

General IconGeneral
BrandABB
ModelREQ650
CategoryProtection Device
LanguageEnglish

Related product manuals