EasyManuals Logo

ABB REQ650 Commissioning Manual

ABB REQ650
150 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #110 background imageLoading...
Page #110 background image
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY) to
simulate CBREADY
Possibly a switch simulation the synchronizing check SESRSYN (25) condition
IED
Trip
BR
SC
ST
SRY
To test
set
+ -
SMBRRECSimulatingtheCBoper
ationbyabistablerelayand =
ANSI09000206_en_1
SMBRREC (79) - CLOSECB
SMBRREC (79) - CBPOS
SMBRREC (79) - CBREADY
ANSI09000206 V1 EN
Figure 17: Simulating the CB operation by a bi-stable relay/breaker simulator and
manual switches
6.7.2.1 Preparation of the verification
1. Check the function settings on the local HMI under Main menu/Settings/IED
Settings/Control/SMBRREC(79,0->1)/SMBRREC:1
If any timer settings are reduced to speed up or facilitate the testing, they shall be set
to normal after testing. A temporary label on the IED can be a reminder to restore
normal settings after which a verification test should be performed.
2. Decide if a synchronizing check function SESRSYN (25) shall be included in the
test.
Section 6 1MRK 505 293-UUS A
Testing functionality
102
Commissioning manual

Table of Contents

Other manuals for ABB REQ650

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB REQ650 and is the answer not in the manual?

ABB REQ650 Specifications

General IconGeneral
BrandABB
ModelREQ650
CategoryProtection Device
LanguageEnglish

Related product manuals