Navigate to Main Menu/Configuration/TCP-IP configuation/
ETHLAN1_AB.
Set values for OperationMode, IPAddress and IPMask. OperationMode must
be set to .
Make sure that the optical fibres are connected correctly.
6.11.1.3 Verifying the station communication
Connect a PC to the substation network and ping the connected IED and the Substation
Master PC to verify that the communication is working up to the transport layer.
The best way to verify the communication up to the application layer is to use a protocol
analyzer connected to the substation or process bus and monitor the communication.
Verifying redundant IEC 61850-8-1 communication
Ensure that the IED receives IEC 61850-8-1 data on both ports A and B. In the local HMI
navigate to Main menu/Tests/Function status/Communication/PRP Status/LAN1–
A / LAN1–B and check that both signals LAN1-A and LAN1-B are shown as Ok. Remove
the optical connection to one of the ports A or B. Verify that either signal LAN1-A or
LAN1-B (depending on which connection that was removed) are shown as Error and that
the other signal is shown as Ok. Be sure to re-connect the removed connection after
completed verification.
6.12 Exit test mode
The following procedure is used to return to normal operation.
1. Navigate to the test mode folder.
2. Change the Enable setting to Disable. Press the 'E' key and the left arrow key.
3. Answer YES, press the 'E' key and exit the menus.
Section 6 1MRK 505 293-UUS A
Testing functionality
118
Commissioning manual