EasyManuals Logo

ABB REQ650 Commissioning Manual

ABB REQ650
150 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #114 background imageLoading...
Page #114 background image
Prepare the IED for verification of settings as outlined in 5.1 "Preparing the IED to verify
settings".
Values of the logical signals for STBRREC (79) are available on the local HMI under
Main menu/Tests/Function status/Control/STBRREC(79,0->1)/STBRREC:1. The
Signal Monitoring in PCM600 shows the same signals that are available on the local HMI.
The purpose of verification before commissioning is to check that entered selections,
setting parameters and configuration render the intended result. The function is flexible
with many options and facilities. At commissioning only the selections and settings
intended for use are verified. If one chooses to reduce some time settings in order to speed
up verification, be careful to set the parameters at intended operational values at the end
of the verification procedure. One such parameter is the reclaim Reset time that must be
timed out before a new test can be performed.
The verification test is performed together with protection and trip functions. Figure
18
illustrates a suggested testing arrangement, where the circuit-breaker (CB) is simulated by
an external bi-stable relay (BR), for example a relay type RXMVB2 or RXMD or Breaker
Simulator from ABB.
Section 6 1MRK 505 293-UUS A
Testing functionality
106
Commissioning manual

Table of Contents

Other manuals for ABB REQ650

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB REQ650 and is the answer not in the manual?

ABB REQ650 Specifications

General IconGeneral
BrandABB
ModelREQ650
CategoryProtection Device
LanguageEnglish

Related product manuals