3.3 Commissioning after taking out of operation
If provided
u Remove cover plates (blind flanges) between compressor casing out-
let and charge air duct, before gas inlet and after gas outlet.
u Inspect exhaust gas duct / line in front of and after turbine for any
combustion deposits, foreign matter or residual water. Clean and re-
move.
u Inspect air supply line or filter silencer for any foreign matter. Clean
and remove.
u Start up turbocharger oil circulation system at engine end.
u Prepare turbocharger for operation as instructed in section "Inspec-
tion work before start-up / commissioning" of chapter headed "Start-
up / commissioning".
u Start up turbocharger.