Use on the field
Amatron+ BAG0082.2 10.10 47
6.5 Cirrus Activ
6.5.1 Procedure for use
1.
Switch on the AMATRON
+
.
2. Select the desired job in the main menu and check the settings.
3.
Start the job.
4.
Select the work menu.
3 tractor control units are available to operate the hydraulic
functions:
Operate tractor control unit 1 (hose marking yellow):
Lower the machine
Move the star wheel to the operational position
Move the preselected track marker to the opera-
tional position
or:
Hydraulic preselection functions
(Obstacle function, keeping star wheel up,: headlands on all
wheels, KG
raising
Operate tractor control unit 2 (hose marking green):
Folding machine extension arms
or:
Hydraulic preselection functions:wheel mark eradicator in
operational position, coulter/harrow pressure
Operate tractor control unit 3 (hose marking blue)
KG folding (only via the folding menu)
oder:
Arbeitstiefe KG
or:
Hydraulic preselection functions: KG
raising
Operate tractor control unit 4 (hose marking red)
Switch blower fan on/off..
5. Check the displayed tramline counter for the first field run and
correct as necessary.
6. Start the sowing.
Electric full dosing:
As soon as the star wheel is lowered to the operational position,
automatic predosing begins.
With
the predosing can be ended prema-
turely..