Use on the field
50 Amatron+ BAG0082.2 10.10
6.6 Cayena
6.6.1 Procedure for use
1.
Switch on the AMATRON
+
.
2. Select the desired job in the main menu and check the settings
3.
Start the job
4.
Select the work menu.
4 tractor control units are available to operate the hydraulic
functions:
Operate tractor control unit 1 (hose marking yellow):
Lower the machine
Operate tractor control unit 2 (hose marking green):
Fold the machine extension arm
Move the track marker to the operational position
Operate tractor control unit 3 (hose marking blue)
Tine coulter working depth
Operate tractor control unit 4 (hose marking red):
Switch the blower fan on/off.
5. Check the displayed tramline counter for the first field run and
correct as necessary.
6. Start the sowing.
When travel in operational position begins, the dosing starts.
Start predosing.
7. After approx. 30 m, stop and check:
depositing depth of the seed
working intensity of the exact harrow
During the sowing, the AMATRON
+
shows the work menu.
From here, all functions relevant to the sowing procedure can be
actuated.
The data determined are stored for the started job.
After use:
1. Check the job data (if required).
2. Activate the control units as required.
3.
Switch off the AMATRON
+
.