Cleaning, maintenance and repairs
12.3 Maintenance plan - overview
• Carry out maintenance work when the first interval is reached.
• The times, running hours or maintenance intervals of any third
party documentation shall have priority.
After the first working run
Component Servicing work
see
page
Workshop work
Tine connection
• Inspect the bolts
75
Hydraulic system
• Inspection for defects
• Inspect for leaks
75
X
Weekly/every 50 working hours
Component Servicing work
see
page
Workshop work
Hydraulic system
• Inspection for defects
75
X
Tine connection
•
Inspect the bolts
73
Roller connection
• Inspect the bolts
74
Disc carrier connection
• Inspect the bolts
74
Scraper on the roller
• Check the distance
63
As required
Component Servicing work
see
page
Workshop work
Coulter
• Replace
72
Tines
• Replace
71
Disc XL041
• Inspect for wear - replace when
the minimum diameter of
360 mm is reached
73
X
Disc segments
• Replace
72
X
Lower link pin
• Replace
77
70
Cenius 03 BAG0144.5 10.19