8.3.1.D Perform Linearity Verification
Available only on the MAX
®
4000XL.
Linearity verification should be done as
dictated by your quality policy.
Performing the verification:
• Press the [PROGRAM] soft key,
highlight the (Factory) IDLE Test
Program, press [ENT], then press
[ESC]. (This sets the instrument idle
temperature to 25 °C).
• From a cold start, allow the instrument
to warm up for 60 minutes before
proceeding.
• Navigate [MENU]CALIBRATION MENUBALANCE CALIBRATION
MENUPERFORM LINEARITY VERFICATION
• Select the PERFORM LINEARITY VERIFICATION menu item.
• The introduction screen is displayed; press [GO] to continue.
• The heat chamber must be less than 30 °C and the cool down fan must be off;
otherwise the verification aborts with a “Too hot” message and must be restarted.
• Follow the instructions. (Two examples are shown on the previous page). During the
weight loading and removal, avoid excess pressure on the balance. Use the
tweezers included with the MAX
®
4000 to gently place the weights on the pan.
• After successful verification, the calibration report is displayed.
• If the verification routine failed or the verification weight value fails, rerun the
verification. If the verification fails again, contact AZI Customer Service.