ascom Ascotel 2025/2045/2065
HBT_20321104_03/B0_en Planning DECT Systems 3.51
Notes:
Take note of safety distances and safety regulations. In areas subject to
explosion hazards take note of the relevant rules and regulations.
This important phase of the project is to be explained in greater detail using an
example.
5.4.3.1 Preparing the Measurements
Factory
2 floors
warehouse /
basement
Administration
5 floors
archive/basement
Porter’s
lodge
haz0331aaena0
Drawing up a situation plan:
• The situation plan records approximately the
number and size of the coverage ranges
required.
• The measurements provide the ideal locations
for the radio units.
Zone 3
Zone 2
Zone 4
Zone 1
Zone 3
Zone 5
haz0347aadea0
Radio supply and zone formation:
• Create a sensible distribution, e.g. several zones
in the factory and administration (porter’s
lodge, basement, etc., in different zones).
• Make a note of the connection capacity
required (number of simultaneous calls) for each
zone to determine the number of radio units
(see also under "Traffic Density", Page 3.56).