11.7 Proper moisture analysis
Before measurement carefully prepare the sample (as described in chapter Description
of Thermogravimetric Analysis) and set correct drying parameters (see chapter Working
Parameters Setting).
m0-m/m0*100% Ts=120C ts= 0:10:00s
T = 32.23C
m= 0.000g
Place an empty single-use pan and
tare the balance with T key.
Open the drying chamber and using
the pan handle place the single-use
t =0:00:00s
m0= 0.000g
0.00 %
pan with the sample on the pan
support. Close the chamber.
START
SET
RAP
MEM
STOP
SAMPLE
T
m0-m/m0*100% Ts=120C ts= 0:10:00s
T = 32.23C
m= 2.033g
Start the measurement choosing
START option (F1 key).
Drying in progress is signalised with
t =0:00:00s
m0= 2.033g
0.00 %
alternating SAMPLE /DRYING
communicate.
START
SET
RAP
MEM
STOP
SAMPLE
F1 F2 F3 F4 F5
m0-m/m0*100% Ts=120C ts= 0:10:00s
T = 32.23C
Wait until END communicate
appears. Now read the result.
Attention: No STB communicate
and m0 sign in negative, marks
m= 2.013g
t =0:00:50s
m0= 2.033g
1.00
%
acceptance of unstable initial mass
value m0, caused by pressing the
pan to chamber wall or by too fast
sample drying, which can cause to
measurement failures.
During the measurement the following information is displayed:
m0-m/m0*100% - mathematic formula used for calculations
T s – defined drying temperature
ts - defined drying time
T – current drying temperature
m – current weight
t – current drying time
m0 – initial weight