Operating manual for BAUER RAINSTAR Series TX Plus 68
...and slacken the PE-pipe by pressing the shut-off lever
downward slowly and carefully.
Switching into gears1 to 4 is only possible when the turbine is rotating!
Shift gear shift lever into the desired position and return the shut-off lever to the “PE-pipe retraction” position.
The reel starts to wind up the PE-pipe.
21.4.1 SPEED ADJUSTMENT
With ECOSTAR 4300 - see page 16
With mechanical speed control - see page 34
21.5 OPERATING MODE II: LAYING DOWN THE PE-PIPE
see page 17
21.5.1 FUNCTIONAL DESCRIPTION OF THE MAIN COMPONENTS
21.5.1.1 MACHINE DRIVE – FULL-FLOW TURBINE
The TX20 full-flow turbine is a specifically designed turbine
model with large cross sections and minimum pressure loss.
Therefore it is also suited for high retraction speeds at very
low flow rates. This turbine features a highly flow-promoting
design and is mounted directly on the reel shaft. It provides
the energy needed for PE-pipe retraction. The turbine speed
is taken directly off the impeller shaft and transmitted over a
V-belt drive to BAUER change-speed gearbox.