HD-973P Series Multi-Level Parking Lift 21 P/N 5900076 — Rev. B3 — January 2024
To create Chalk Line Guides:
Create the Front Chalk Line where you want the Front of the Lift.
Make the Front Chalk Line longer than the Total Width setting for your Lift.
Create the Powerside and Offside Chalk Lines at 90° angles to the Front Chalk Line and parallel to
each other. Make the Powerside and Offside Chalk Lines longer than the Outside Posts Length
setting for your Lift model.
The Powerside and Offside Chalk Lines must be parallel to each other.
Create the Rear Chalk Line parallel to the Front Chalk Line. Make the Rear Chalk Line longer than
the Total Width setting for your Lift model.
The Front and Rear Chalk Lines must also be parallel to each other.
Before moving the Posts into position, measure diagonally to make sure the two diagonal
measurements are the same. This ensures your layout is correct.
Do not forget to check the diagonals.
When you move the Posts into position, put the corners of the Base Plates inside the corners
created by the four Chalk Lines.
Unloading and Unpacking
Once the components are unloaded, they are your responsibility to move around. As the Lift includes a
number of heavy pieces, the closer you unload them to the installation location, the better off you are.
⚠ CAUTION Some Lift components are very heavy; if handled incorrectly, they can damage
materials like tile, sandstone, and brick. Try to handle the Lift components twice:
once when delivered and once when moved into position. You must have a Forklift
or Shop Crane to move them into position. Use care when moving them.
⚠ WARNING The Posts and Runways are delivered with stabilizing structures on each end. Be
very careful when removing these stabilizing structures; the Posts and Runways
can shift or even fall. If they fall on a person, they could cause severe injury.