6 - ELECTRICAL CONNECTION
Please refer to the certied dimensional drawings, supplied with 
the unit.
6.1 - Power supply
The  power  supply  must  meet  the  specication  on  the  unit's 
nameplate. 
The  supply  voltage  must  be  within  the  range  specied  in  the 
electrical data table.
For connections, refer to the wiring diagrams and certified 
dimensional drawings.
WARNING:
Operation of the unit with an incorrect supply voltage or 
excessive  phase  imbalance  constitutes  misuse  which  will 
invalidate the manufacturer's warranty. If the phase imbalance 
exceeds 2% for voltage, or 10% for current, contact your local 
electricity supplier at once and ensure that the unit is not 
switched on until corrective measures have been taken.
After the unit has been started up, the power supply must only be 
disconnected  for  quick  maintenance  operations  (one  day 
maximum). For longer maintenance operations or when the unit 
is taken out of service, the power supply of the unit must be 
maintained permanently (the heaters must be powered on).
Specic data 30RQ/30RQP
Otherwise,  the  suction  shut-o  valves  on  each  circuit  must  be 
closed.
6.2 - Voltage phase imbalance (%)
100 x max. deviation from average voltage 
Average voltage
Example:
On a 400 V - 3 ph - 50 Hz supply, the individual phase voltages 
were measured with the following values:
AB = 406 V; BC = 399 V; AC = 394 V
Average voltage  = (406 + 399 + 394)/3
  = 1199/3
    = 399.7 i.e. 400 V
Calculate the maximum deviation from the 400 V average:
(AB) = 406 - 400 = 6
(BC) = 400 - 399 = 1
(CA) = 400 - 394 = 6 
The maximum deviation from the average is 6 V. The greatest 
percentage deviation is: 100 x 6/400 = 1.5%
This is less than the permissible 2% and is therefore acceptable.
6.3 - Power connection/disconnect switch
The power connection of the unit is carried out at a single point 
upstream of the unit’s disconnect switch.
6.4 - Recommended cable sections
Wire sizing is the responsibility of the installer, and depends on 
the characteristics and regulations applicable to each installation 
site. The following is only to be used as a guideline, and does not 
make the manufacturer in any way liable. 
After wire sizing has been completed, using the certied dimensional 
drawing, the installer must verify the appropriate means of 
connection and dene any modications necessary on site.
The connections provided as standard for the customer-supplied 
power supply cables are designed for the number and type of 
cables listed in the table below.
The calculations of favourable and unfavourable cases are 
performed by using the maximum current possible for each unit 
tted with a hydraulic module (see the tables of electrical data for 
the unit and the hydraulic module).
The study includes the standardised installation cases according 
to IEC 60364: Cables with PVC (70 °C) or XLPE (90 °C) insulation 
with copper core; routing in accordance with table 52C of the 
standard. 
The maximum length mentioned is calculated to limit the voltage 
drop to 5%.
IMPORTANT:
Before connecting the main power cables (L1 - L2 - L3), always 
check 3 phases are in the correct order (clockwise) before 
proceeding to the connection on the main disconnect switch.
Motor
25