III. SYSTEM START-UP (to be completed by the start-up technician)
A. PRE-START CHECK
1. ALL SERVICE VALVES OPEN.
YES NO
2. COMPRESSOR OIL LEVEL IS CORRECT.
YES NO
3. VERIFY COMPRESSOR MOUNTING BOLT TORQUE IS
10 TO 14 ft-lbs (13.5 TO 18.9 N-m)
YES NO
4. LOCATE, REPAIR, AND REPORT ANY LEAKS. _______________________________________________
________________________________________________________________________________________
5. SUPPLY VOLTAGE IS WITHIN UNIT NAMEPLATE RANGE.
YES NO
6. CONTROL TRANSFORMER(S) PRIMARY CONNECTION SET
FOR PROPER VOLTAGE.
YES NO
7. CONTROL TRANSFORMER (TRAN1) SECONDARY VOLTAGE ________________ vac
CONTROL TRANSFORMER (TRAN2) SECONDARY VOLTAGE ________________ vac
8. CHECK VOLTAGE PHASE IMBALANCE:
AB: ______ V AC: ______ V BC: ______ V
AVERAGE VOLTAGE (AB + AC + BC)/3: ______ V
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE: ______ V
VOLTAGE IMBALANCE: MAXIMUM DEVIATION/AVERAGE VOLTAGE x 100 ______ %
9. VOLTAGE IMBALANCE LESS THAN 2%.
YES NO
DO NOT START UNIT IF VOLTAGE IMBALANCE IS GREATER THAN 2%.
CONTACT LOCAL UTILITY FOR ASSISTANCE.
10. EVAPORATOR FAN SWITCH(ES) OPERATIONAL, IF INSTALLED.
N/A YES NO
11. PROPER CONDENSER FAN ROTATION CONFIRMED.
YES NO
12. PROPER EVAPORATOR FAN ROTATION CONFIRMED.
YES NO
13. RECORD SOFTWARE VERSION INFORMATION.
PRESS [ENTER] AND [ESCAPE] TO OBTAIN SOFTWARE VERSIONS.
YES NO
Run Status
o
VERS
SOFTWARE VERSION NUMBERS
MBB CESR131466— __________ — ____________
AUX CESR131333— __________ — ____________
CXB CESR131173— __________ — ____________
EMM CESR131174— __________ — ____________
MARQ CESR131171— __________ — ____________
NAVI CESR130227— __________ — ____________
14. TIME AND DATE SET PROPERLY. YES NO