IMPORTANT: The CP6000 CMT and the conduit must be secured in place to prevent them
from moving out of position while the concrete is poured and curing.
10. Pour the concrete.
Note: Make sure the concrete surface between the conduits is completely level and free of any
irregularities.
11. Refer to the measurements in this guide and ensure the anchor rod locations are correct before the
concrete is dry.
12. Use a level to ensure the bolts are plumb.
You are now ready to install the CP6000 pedestal mount charging station.
33
Installation into New Concrete