EasyManua.ls Logo

Cisco ONS 15454 - NTP-A 13 Perform the Shelf Installation Acceptance Test

Cisco ONS 15454
62 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
1-60
Cisco ONS 15454 Procedure Guide, R4.0
March 2003
Chapter 1 Install the Shelf and Backplane Cable
NTP-A13 Perform the Shelf Installation Acceptance Test
NTP-A13 Perform the Shelf Installation Acceptance Test
Step 1 Complete Table 1-9 by verifying that each applicable procedure was completed.
Step 2 Complete the “DLP-A32 Inspect the Shelf Installation and Connections” task on page 1-61.
Step 3 Complete the “DLP-A33 Measure Voltage” task on page 1-61.
Step 4 Continue with the “NTP-A15 Install the Common Control Cards” procedure on page 2-2.
Stop. You have completed this procedure.
Purpose Use this procedure to perform a shelf installation acceptance test.
Tools/Equipment Voltmeter
Tools/Equipment Oval and/or block ferrites
Prerequisite Procedures Applicable procedures in Chapter 1
Required/As Needed Required
Onsite/Remote Onsite
Security Level None
Table 1-9 Shelf Installation Task Summary
Description Completed
NTP-A1 Unpack and Inspect the ONS 15454 Shelf Assembly, page 1-4
NTP-A2 Install the Shelf Assembly, page 1-5
NTP-A3 Open and Remove the Front Door, page 1-12
NTP-A4 Remove the Backplane Covers, page 1-15
NTP-A5 Install the Electrical Interface Assemblies, page 1-16
NTP-A6 Install the Power and Ground, page 1-23
NTP-A7 Install the Fan-Tray Assembly, page 1-29
NTP-A119 Install the Alarm Expansion Panel, page 1-31
NTP-A8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections, page 1-34
NTP-A120 Install an External Wire-Wrap Panel to the AEP, page 1-40
NTP-A9 Install the Electrical Card Cables on the Backplane, page 1-45
NTP-A10 Route Electrical Cables, page 1-53
NTP-A11 Install the Rear Cover, page 1-55
NTP-A12 Install Ferrites, page 1-57