MAN.241 Rev.5 ENG - Use and maintenance manual S23 page 51 of 127
2. couple the 110/120/230 V plug (power line) to
the connector on the machine and press the
appropriate button of the magnetothermic
switch;
3. now the batteries will be in charge and the
charge progress can be evaluated through the
leds on chassis box or on radio control station.
The charge times are:
BATTERY CHARGE
TIME
0% - 80%
4 h
80%-100%
2 h
With a full charge (100%), the 160 Ah battery pack is
able to perform at least 10 work cycles. A work cycle
includes the following sequence of operations:
1) stabilization;
2) complete machine development;
3) complete machine return;
4) destabilization.
At the end of each working session and
however at least every 15 days, if the
MEWP is not used, absolutely recharge the
battery pack.
4.6 Emergency manoeuvres
Before starting the emergency procedures, it
could be useful to contact C.M.C. Service and
communicate errors data.
In case of emergency, the controls of the MEWP
aerial part can be performed by the operator on the
ground.
4.6.1 Emergency buttons

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the CMC S23 and is the answer not in the manual?

CMC S23 Specifications

General IconGeneral
BrandCMC
ModelS23
CategoryLifting Systems
LanguageEnglish

Related product manuals