Preventive maintenance - ACC
45
HS-RC-C5E-ACC_01.fm
00/0309
7.4 ACC: door closing and seal efficiency check
Arm Controller Cabinet
Front view
Status: Irrelevant
Material: Not required
Equipment: Not required
Preliminary procedures / notes
The cabinet door shall remain closed to guarantee the efficiency of the cooling
system and prevent contamination from entering in the cabinet. Thanks to the
structure, the IP 54 procetction category of the cabinet guarantees such
efficiency level.
The deterioration of the seal performances may have a detrimental impact on this
situation.
Operating procedure
a. Check the seals efficiency and the correct positioning in their seat along the
entire door perimeter.
b. If necessary, replace the seals.
Follow-up procedure
Not required

Table of Contents

Other manuals for Comau Robotics C5G

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Comau Robotics C5G and is the answer not in the manual?

Comau Robotics C5G Specifications

General IconGeneral
BrandComau Robotics
ModelC5G
CategoryControl Unit
LanguageEnglish