MACHINE PREPARATION
1. HANDLING THE PACKED MACHINE
The machine is contained in specific packaging with a pallet for the handling with
fork trucks. The packages cannot be placed on top of each other.
The total weight is 1100kg
The overall dimensions of the package are:
C130D
A: 2050 mm
B: 1520 mm
C: 2380 mm
A
C
B
2. HOW TO UNPACK THE MACHINE
1. Remove the outer packaging
2. The machine is fixed to the pallet with wedges which block the wheels
3. Remove these wedges
4. Use a chute to get the machine down from the pallet, pushing it backwards.