7-150
2. Remove the 5 screws from the FR4 board, as shown in the following figure. (The FR4 board is not needed
after the installation of the power terminal kit). Screw Torque: 12–15 kg-cm / (10.4–13 lb-in) / (1.2–1.5 Nm)
Figure 7-231
Figure 7-232
3. Loosen the upper M8 nuts (1–6) with a sleeve wrench (12mm of the sleeve). M8 Torque: 90kg / (78.1 lb-in) /
(8.8 Nm)
Figure 7-233
4. Install the 3 pcs copper assy., as shown in the Figure 234. Tighten the upper M8 nuts (1–6) with a sleeve
wrench (12mm of the sleeve), as shown in the Figure 235 below.
M8 Torque: 180 kg-cm / (156.2 lb-in) / (17.65 Nm)
FR4 Board
Copper assy. installation completed
Figure 7-235
Figure 7-234
Figure 7-236