User Information Ringlock ScaoldingErectionGuidelines
999817902 - 11/2020
13
Step 7
➤ Alternatively,installadvancedGuardrailsinthelift
aboveutilizingregularRinglockLedgers,ourrec-
ommendationwouldbetouseproprietaryScaold
Steps. It is recommended that both levels of Guard-
rail are installed at the same time using the
ScaoldStep.
Advanced guardrail using ringlock ledgers
installed
Step 8
➤ If the temporary lift (Step 7) has been used then
movePlanksuptoworkinglift,addthetoeboards
which slot behind the wedge. The erection is now
complete.