Step 11
➤ Remove temporary platform Planks from Stair Tow-
er.
➤ Assemble 1.0m Standard at the top closest to the
topofthePlatformStairs,thissupportstheOuter
Guardrailforthenallift.
➤ AssemblethetwoOuterGuardrailAdaptorsonto
the top Standard if applicable.
➤ AssembletheOuterGuardrailwhichwillattachto
the rosette on the Standards.
➤ AssembleInternalGuardrailExtendedontothetop
PlatformStairs,AssembleInternalGuardrailonto
the rest of the Platform Stairs throughout the Tower.
UseatypicalscaoldSpannertotightenthetwo
bolts. Internal Guardrails are to be located on the
internal side rail of the Platform Stairs directly un-
derneath the second Tread (See detail).
The tower is now complete up to the third lift.
Continue with is method until the full height of
the Stair tower is reached.