Aluminium Stair Tower Erection Guidelines (4-Leg) User Information Ringlock
999817902 - 11/2020
34
Step 11
Remove temporary platform Planks from Stair Tow-
er.
Assemble 1.0m Standard at the top closest to the
topofthePlatformStairs,thissupportstheOuter
Guardrailforthenallift.
AssemblethetwoOuterGuardrailAdaptorsonto
the top Standard if applicable.
AssembletheOuterGuardrailwhichwillattachto
the rosette on the Standards.
AssembleInternalGuardrailExtendedontothetop
PlatformStairs,AssembleInternalGuardrailonto
the rest of the Platform Stairs throughout the Tower.
Useatypicalsca󰀨oldSpannertotightenthetwo
bolts. Internal Guardrails are to be located on the
internal side rail of the Platform Stairs directly un-
derneath the second Tread (See detail).
The tower is now complete up to the third lift.
Continue with is method until the full height of
the Stair tower is reached.
For notes on dismantling the Ringlock Stair
Tower refer to”Guidelines to Dismantling Rin-
glockSca󰀨olds”onpage21.