Stair Tower Erection Guidelines (10-Leg) User Information Ringlock
999817902 - 11/2020
26
Step 7
Thethirdlandingcanbeassembledbythenextcon-
secutive steps:
Place the 3.0m Standards.
Assemble the Ledgers.
Assemble the Bay Braces at the two outer sides.
Assemble the Stringers.
Assemble the Treads from bottom to top.
AssemblethePlanksonthenextlanding.
Step 8
The Stair Tower is complete after the assembly of
1mStandardsonthethirdlanding,Guardrails(Using
Ledgers)alongthestairandonthethirdlanding,and
Toeboards on the third landing.
The tower is now complete up to the third lift. Contin-
ue with is method until the full height of the Stair tower
is reached.
For notes on dismantling the Ringlock Stair Tower re-
ferto“GuidelinestoDismantlingRinglockSca󰀨olds”
on page 21.