Aluminium Stair Tower Erection Guidelines (4-Leg) User Information Ringlock
999817902 - 11/2020
32
Step 5
➤ AttachtheOuterGuardrailframeontothersttwo
Rosettes of the Standard closest to the base of the
PlatformStairs.TheOuterGuardralhasswivelTer-
minals for this purpose (See Detail).
➤ RepeatItem1atthetopoftheOuterGuardrail
using the swivel Ledgerheads. Secure horizontal
wedgewithablowofahammer,thiswillprevent
the Guardrail from lifting/ sliding.
➤ Insert two Steel Planks 1.40m long to create a tem-
porary platform.
Step 6
Thenextassemblyinstructionsrequirethetempo-
rary platform described in Step 5. It is recommended
thatthescaolderusesasafetyharnessand55mm
scaoldhookattachedtoalanyardwhentraversing
onto the temporary platform from the Platform Stairs.
Careisrequiredsteppingacrossthelargegap.Oruse
suitable ladder from bottom planked level to access
temporary platform.Refer to section ‘Safety Harness
Connection Points’ for more information. Reference to
the HSE Work at Height Regulation and Safety Guid-
ance Notes provided by the NASC is recommended.
➤ From the available temporary platform assemble
thenextsetofStandards.
➤ Assemble the Ledgers and Transoms
➤ Assemble Diagonal Braces on all outside faces of
the bay.
Thetowerisnowreadytoassemblethenextlift.