NOTE: For more than four (4) pump loops use the manufacturer’s distribution box. Pump
communication conduit is not required if the manufacturer's distribution box is located near the
remote DPC enclosure.
6. Attach Line, Neutral and Ground wires from the breaker panel to the power-connection block.
7. Attach pump communication wires to each pump loop on CN5. See the illustration above for up to four
(4) pumps connected directly to connector CN5 of the DPC board. For more than four (4) pump loops
use the manufacturer’s distribution box (see below for connections to Wayne and Gilbarco distribution
boxes).
8. Connect the RJ45 connector to CN4.
3.1.6.1 Wayne Data Distribution Box Connection to DPC Board
Wayne Data Distribution Box connected to DPC interface.