Front Panel Configuration
35
Page FPE ID Parameter Values
414 LCD Page Timer hh:mm:ss
413 LCD Scroll Timer hh:mm:ss
SCHEDULER
501 Scheduler Enable Disabled (0) Enabled (1)
502 Scheduler Bank 1 Run Mode Off Load (0) On Load (1) Do Not Transfer (2)
503 Scheduler Bank 1 Period Weekly (0) Monthly (1)
504 Scheduler Bank 1 Event 1 Day 1-7 (Day, 1=Monday)
505 Scheduler Bank 1 Event 1 Start Time hh:mm
506 Scheduler Bank 1 Event 1 Duration hh:mm
507 Scheduler Bank 1 Event 2 Day 1-7 (Day, 1=Monday)
508 Scheduler Bank 1 Event 2 Start Time hh:mm
509 Scheduler Bank 1 Event 2 Duration hh:mm
510 Scheduler Bank 1 Event 3 Day 1-7 (Day, 1=Monday)
511 Scheduler Bank 1 Event 3 Start Time hh:mm
512 Scheduler Bank 1 Event 3 Duration hh:mm
513 Scheduler Bank 1 Event 4 Day 1-7 (Day, 1=Monday)
514 Scheduler Bank 1 Event 4 Start Time hh:mm
515 Scheduler Bank 1 Event 4 Duration hh:mm
516 Scheduler Bank 1 Event 5 Day 1-7 (Day, 1=Monday)
517 Scheduler Bank 1 Event 5 Start Time hh:mm
518 Scheduler Bank 1 Event 5 Duration hh:mm
519 Scheduler Bank 1 Event 6 Day 1-7 (Day, 1=Monday)
520 Scheduler Bank 1 Event 6 Start Time hh:mm
521 Scheduler Bank 1 Event 6 Duration hh:mm
522 Scheduler Bank 1 Event 7 Day 1-7 (Day, 1=Monday)
523 Scheduler Bank 1 Event 7 Start Time hh:mm
524 Scheduler Bank 1 Event 7 Duration hh:mm
525 Scheduler Bank 1 Event 8 Day 1-7 (Day, 1=Monday)
526 Scheduler Bank 1 Event 8 Start Time hh:mm
527 Scheduler Bank 1 Event 8 Duration hh:mm
528 Scheduler Bank 2 Run Mode Off Load (0) On Load (1) Do Not Transfer (2)
529 Scheduler Bank 2 Period Weekly (0) Monthly (1)
530 Scheduler Bank 2 Event 1 Day 1-7 (Day, 1=Monday)
531 Scheduler Bank 2 Event 1 Start Time hh:mm
532 Scheduler Bank 2 Event 1 Duration hh:mm
533 Scheduler Bank 2 Event 2 Day 1-7 (Day, 1=Monday)
534 Scheduler Bank 2 Event 2 Start Time hh:mm
535 Scheduler Bank 2 Event 2 Duration hh:mm
536 Scheduler Bank 2 Event 3 Day 1-7 (Day, 1=Monday)
537 Scheduler Bank 2 Event 3 Start Time hh:mm
538 Scheduler Bank 2 Event 3 Duration hh:mm
539 Scheduler Bank 2 Event 4 Day 1-7 (Day, 1=Monday)
540 Scheduler Bank 2 Event 4 Start Time hh:mm
541 Scheduler Bank 2 Event 4 Duration hh:mm
542 Scheduler Bank 2 Event 5 Day 1-7 (Day, 1=Monday)
543 Scheduler Bank 2 Event 5 Start Time hh:mm
544 Scheduler Bank 2 Event 5 Duration hh:mm
545 Scheduler Bank 2 Event 6 Day 1-7 (Day, 1=Monday)
546 Scheduler Bank 2 Event 6 Start Time hh:mm
547 Scheduler Bank 2 Event 6 Duration hh:mm
548 Scheduler Bank 2 Event 7 Day 1-7 (Day, 1=Monday)
549 Scheduler Bank 2 Event 7 Start Time hh:mm
550 Scheduler Bank 2 Event 7 Duration hh:mm
551 Scheduler Bank 2 Event 8 Day 1-7 (Day, 1=Monday)
552 Scheduler Bank 2 Event 8 Start Time hh:mm
553 Scheduler Bank 2 Event 8 Duration hh:mm